How to Read a PVsyst Report Before You Sign
Author
Hisham Abdalla
Date Published

Disclaimer: Research and analysis by the engineering team. Sources referenced below. The worked examples use hypothetical inputs chosen for the arithmetic, not data from any real bid.
A PVsyst report is the printout of a simulation. It states how many kilowatt hours per kilowatt peak a design should produce in an average year, and every figure in it rests on inputs the bidder chose. Read it in order: site and weather file, orientation and shading, system, losses, results, then P50 and P90. Look hardest at the weather source, the soiling assumption and the availability assumption.
Two bids for the same roof can differ in predicted yield by 7 percent with identical equipment, as the worked example below shows. The difference sits in a handful of lines that most readers skip.
Our guide to running a solar tender tells you to ask every bidder for the energy simulation and its inputs. Here is what to do when it arrives.
What a PVsyst Report Is, and What It Is Not
PVsyst is simulation software from PVsyst SA. Its documentation lists the printable forms a report is built from: the general and detailed simulation parameters, the main results, the loss diagram, and any graphs the user chooses. A report is a prediction for a typical year, and nothing in it has been measured.
It shows what the bidder entered. PVsyst's documentation says its loss parameters start from default values and advises defining each one for the actual system after the first simulation, so a report may carry defaults nobody tuned to your site. The weather behind it is a long-term average, so a real year will differ. And the report says nothing about the contract: a predicted yield becomes a guarantee only if the contract says so, and our article on the solar EPC contract covers how a performance ratio guarantee is written and tested.
Ask for the full PDF with the parameter pages, the PVsyst version and the variant name. Better still, ask for the project file so your engineer can re-run it with your own assumptions.
Site, Weather Source and Orientation
Start with the coordinates and altitude. They should match your site, not the bidder's office or a nearby city. Then find the line naming the weather data: the provider, its version and the years it covers.
PVsyst's documentation names weather data as the dominant contributor to uncertainty in a yield estimate. Its comparison of weather providers found that sources typically agree within 10 percent of their mean, and that it is hard to say which is closest to reality. A file marked synthetic is not necessarily wrong. PVsyst builds synthetic hourly data from monthly averages, which suits an annual estimate and is a poor basis for judging a ten day test.
You can cross-check the weather line for free. The European Commission's PVGIS covers Africa with METEOSAT satellite data. Its documentation warns that dust storms are hard to detect in satellite images and that short-term changes in aerosols are not well captured, and it lists dust and dirt among the effects PVGIS does not model. So use it to test the irradiation line, never the soiling line. If the report's annual irradiation on the tilted plane sits more than 10 percent above PVGIS for the same coordinates, we would ask the bidder why.
Then check orientation and shading. Tilt and azimuth should match the roof drawings. Ask for the shading scene and the near shading loss. A shading line of zero on a roof with plant rooms, parapets and water tanks is wrong.
Specific Yield and Performance Ratio, Defined
Specific yield is the annual energy delivered to the grid divided by the installed kWp, in kWh per kWp per year. PVsyst calls it specific production, and it is the final yield of the IEC 61724 indicators on a yearly scale. It depends on the weather and the orientation, so use it to compare bids for the same site.
The performance ratio (PR) is the energy delivered divided by the energy the array would deliver at its nameplate rating under the irradiation it received, which PVsyst defines as the energy to the grid divided by the incident irradiation times the nominal power. PVsyst says it is not directly dependent on weather data or orientation, so it can compare system quality between sites. Note the word directly. Temperature losses sit inside PR, so a hot site reads lower than a cool one with the same hardware, and rear-side gain on bifacial modules pushes it up. Use both numbers together.
Take a hypothetical 1,000 kWp roof with 2,150 kWh per m2 of irradiation in the plane of the array each year. Bid A reports 1,826,651 kWh to the grid, a specific yield of 1,827 kWh per kWp and a PR of 1,827 / 2,150 = 0.850. Bid B reports 1,700,613 kWh, a specific yield of 1,701 kWh per kWp and a PR of 1,701 / 2,150 = 0.791. Bid A claims 7.4 percent more energy from the same roof.
The IFC's 2011 utility-scale solar guide, written for India, gives context. It puts the PR of a well-designed plant typically in the region of 75 to 85 percent. It gives about 77 percent in summer and 82 percent in winter, 80 percent on average, as unremarkable for a plant not operating in high ambient temperatures. Bid A at 85.0 percent sits at the top of that range. In a hot climate, it needs an explanation.
Reading the Loss Diagram From the Top
The loss diagram runs from the irradiation falling on the roof down to the energy injected to the grid. PVsyst's loss diagram documentation notes that each loss is a percentage of the previous energy quantity, so the percentages do not add. Two losses of 5 percent are 9.75 percent, not 10. Multiply the remaining fractions, which is also how PR is built.
Here is what Bid A and Bid B show, as percentage losses. Both have incidence angle 2.0, irradiance level 0.5, temperature 8.0, mismatch 0.8, DC wiring 1.0, inverter 2.2 and AC wiring 0.4. They differ on three lines.
Soiling. Bid A uses 1.0 percent and Bid B uses 5.0 percent.
Light-induced degradation (LID). Bid A has none and Bid B has 2.0 percent.
Unavailability. Bid A has none and Bid B has 1.0 percent.
Multiplying the fractions for Bid A gives 0.980 x 0.990 x 0.995 x 0.920 x 0.992 x 0.990 x 0.978 x 0.996 = 0.850. Bid B swaps in its soiling figure, adds the other two lines and gives 0.791. Replace Bid A's three lines with Bid B's and its PR falls to 0.791 as well. The equipment did not differ. Three assumptions did.

Two hypothetical bids for the same 1,000 kWp roof with identical equipment. Three loss assumptions explain the 7.4 percent gap in predicted yield. Source: MIMAH engineering practice; loss definitions from the PVsyst documentation.
Soiling, Temperature, Degradation and Availability
Each of these lines is an assumption the bidder sets, and PVsyst's documentation of array and system losses says what it knows about each.
Soiling. PVsyst says soiling depends strongly on rainfall, calls it negligible, under 1 percent, in moderately rainy climates such as Central Europe, and lets users enter monthly values. A flat 1 percent in a dusty climate looks like that temperate number carried over. Ask for the monthly soiling table and the cleaning schedule it assumes. Our guide to panel maintenance in dusty climates covers how often arrays need washing.
Temperature. PVsyst puts typical module power loss at 0.2 to 0.4 percent per degree Celsius above 25 degrees. A module running at 65 degrees is 40 degrees above that, so at that moment it loses 8 to 16 percent. The annual temperature line comes from a thermal model whose heat transfer coefficients PVsyst says must be fitted to real system data. Ask what coefficients the bidder used and for what mounting.
LID. PVsyst puts LID at typically 1 to 3 percent for conventional p-type crystalline modules, does not propose a default, and suggests 2 percent if a value is entered. A bid with no LID line either uses modules not affected, such as n-type, or has left it at zero. Ask which.
Degradation. PVsyst simulates a chosen year of the system's life. Its documentation says the manufacturer's warranty curve is a lower limit for any individual module and not the right basis for an average. A report for year one overstates the average over a 20 year contract. Field data in our guide to panel degradation put the median near 0.5 percent a year, and the contract needs to say which year the guaranteed PR refers to.
Unavailability. PVsyst can switch the system off for a time fraction or a number of days. A zero line says the plant never stops, which does not match any O&M contract. Compare the line with the availability the O&M provider will actually guarantee.
P50 and P90, With the Arithmetic
P50 is the annual energy the plant has a 50 percent probability of exceeding. P90 is the level it has a 90 percent probability of exceeding, so it is the cautious figure. PVsyst's P50 and P90 page assumes annual yields follow a normal distribution centred on the simulation result, adds the individual uncertainties in quadrature, and states that P90 lies 1.28 standard deviations below the mean. The formula, with the more precise multiplier of 1.282, is:
P90 = P50 x (1 - 1.282 x relative uncertainty)
Take Bid B with a P50 of 1,701 kWh per kWp. Suppose its relative uncertainties, each at one standard deviation, are weather variability 3.5 percent, irradiance data 4.0 percent, PV model and parameters 3.0 percent, and soiling and other items 2.0 percent. PVsyst says year-to-year variability of annual irradiation is typically 3 to 4 percent, so 3.5 is in range.
Combined in quadrature the uncertainty is the square root of (3.5 squared + 4.0 squared + 3.0 squared + 2.0 squared). That is the square root of (12.25 + 16 + 9 + 4) = the square root of 41.25 = 6.42 percent. P90 = 1,701 x (1 - 1.282 x 0.0642) = 1,701 x 0.9177 = 1,561 kWh per kWp, which is 8.2 percent below P50.
Three cautions apply. First, ask whether a quoted uncertainty is one standard deviation or already scaled to the P90 level. A figure of plus or minus 8.2 percent at P90 equals 6.4 percent at one standard deviation.
Second, ask whether the P90 is for one year or for ten. If year-to-year weather is independent, the weather term for a ten year average shrinks by the square root of 10, from 3.5 to 1.11 percent, while the other terms stay. The total becomes the square root of (1.11 squared + 16 + 9 + 4) = 5.50 percent, and the P90 rises to 1,701 x (1 - 1.282 x 0.0550) = 1,581 kWh per kWp. Two bids with the same inputs can differ by 20 kWh per kWp on this choice alone.
Third, PVsyst says its tool does not capture bias in the weather file and recommends running several providers to gauge it, and that P50 and P90 are meaningful only for annual totals, not for months or days.

From P50 to P90 on a hypothetical bid, combining uncertainties in quadrature, using the P90 relationship in the PVsyst documentation. Source: PVsyst, P50 and P90 evaluations; MIMAH engineering practice.
Red Flags When Two Bids Disagree
Different weather files. If Bid A uses one provider and Bid B another, part of the gap is data, not design. Make both use the same file.
A temperate soiling figure in a dusty site. Check the monthly table and the cleaning interval.
Missing lines. No LID, no degradation year, no unavailability. Each is a small number on its own and together they add up to several percent.
A PR above the usual range for a hot climate. Compare it with the IFC's 75 to 85 percent, and expect a hot site to sit lower. That range dates from 2011, so if the bid uses bifacial modules, ask how much of the PR is rear-side gain.
Losses that differ without a hardware difference. Same modules, same inverter, same tilt, and different wiring or mismatch losses.
A P90 with no breakdown. Ask for the list of uncertainties and whether it covers one year or ten.
A yield the contract does not guarantee. A report is evidence, not a guarantee. Our guide to monitoring covers the irradiance and energy measurements that let you test it later, and the tariff in a PPA depends on the same yield, as our article on solar PPA rates shows.

Red flags to check when two PVsyst reports disagree. The PR range is the IFC's figure for a well-designed utility scale plant. Source: IFC, Utility Scale Solar Power Plants (2011); MIMAH engineering practice.
What to Ask Each Bidder to Send
Ask every bidder to re-run the simulation with your inputs: the same weather file and period, the same monthly soiling, the same availability, the same degradation year and the same P90 basis. We would also ask for the PAN and OND files, PVsyst's module and inverter data files, because a report can only be as honest as those. Then compare PR and specific yield.
A gap that survives the re-run comes from equipment or design. A gap that disappears came from assumptions, and the bid that looked better was better only on paper.
MIMAH's renewable energy team reviews yield simulations as part of feasibility studies and performance audits. If you hold two PVsyst reports that do not agree, get in touch and we will go through the inputs with you.